Wednesday, December 14, 2011

Stats update 14 Dec 2011

Below is a list of all the Projects completed, in progress & pending...

All up we expect to have completed total of 407 by Mid January 2012, with an additional approx 108 to be completed approx mid March. (grand total will be around 515 cisterns - & counting!!)

Average family size is in our communities is 7 members, x 515 = 3605 (this figure is conservative as many of the cisterns have been placed in schools with average number of beneficiaries being 80).

Projects in Process:
Sapasma Project II mxn$435399
18 cisterns in Los Torres (Phase III in this community) Pilot completed 14-18th Nov, individual cisterns to be completed by mid January 2012
21 Cisterns in Presita de Santa Rosa (Pilot paid for by private donation - thankyou Chris Hosford, 20 cisterns funded by Sapasma)
18 Cisterns in Cienega Juana Ruiz (Phase II in this community)
2 Cisterns in Lomas de Cocina
1 Cistern in Cinco Senores
(all of these cisterns are expected to be completed by mid January.

Project Pending:
$65.3k global grant application stage with Chinook RC in Calgary Alberta Canada, with contribution of $20k by Alberta Government from their Community Initiative Project - Thankyou CIP!
This is to be approx 108 cisterns constructed in 3 communities -
Tallahassee RC has pledged a further $10k to help bridge the price increase in materials since the budget was presented

The projects below have all been completed...
347 to date with more plus the additional ones in construction & in planning.

Tierra Blanca 28
Juan Gonzalez 22
funded by Global Grant from Baton Rouge Capitol City RC & District 6200 US$33,500
(completed June 2011)

Tierra Blanca 14 - direct grant donation from New Braumfels RC $2k, & Port Lavaca RC $7k
(completed June 2011)

San Lorenzo 4
Cinco Senores 11 (incl pilot in JG)
Fondo Verde Mxn$150k
(Completed June 2011)

Villa de Guadalupe 27
Cienega Juana Ruiz 26
Sapasma mxn$435k
(completed June 2011)

Villa Pilot x1
Cienega Pilot x 1
Bellingham RC US$1500
(completed June 2011)

Tierra Blanca completed all 42 cisterns in record time of 5 weeks!!

Water Projects completed from 1st Jan 2009 - March 2011

Los torres 52 cisterns - done in several phases.

Phase II Project : $21,200
Direct Grant Rotary Club Partners amount committed:
RC SMA Midday Mexico 200
Tallahassee RC USA (Bill Webb) 4000
RC of Sechelt BC Canada (Tom Pinfold) 5000
Paso Robles RC USA (Robert Lata) 500
Tyron RC (Jerry Atkins) 5000
RC of Ann Arbor (Len Stringer) 6000
US$ Total of Rotary funds committed 20700
Plus! $500 donation from Skymed/Linda Scholey $500
(this funded 27 in this phase + excess $$ funded 4 extra cisterns & 3 rotoplas added to the phaseIII)

Phase III project: $12,200
SMA Midday 200
Tallahassee 1000 DDF 2000
Tyron RC 2500 DDF 2500
Ann Arbour 1500
Sechelt 1500
Trail BC 1000 N/A
Subtotals, Cash and DDF 7700 4500
San Miguel Community Fund (SMCF) funding grant 1 $2468 SMCF funding grant 2 2235,
(this funded 17 cisterns)


Montecillo de Nieto 30 cisterns $16700
SMA Midday 200
Tallahassee 5000 DDF 11500
Unitarian Universalists funded 4 months of organisation in this community. $400 per month.
Vivienda de Arriba 17 cisterns & Cruz del Palmar 28 cisterns for a combined $24700
SMA Midday $200
RC West U $4500
RC Richmond $3500 District 5890 8,000
RC Tallahassee 2000 DDF 6940 6,500
Subtotals, Cash and DDF 10200 14,500


Capaderillo 40 cisterns $21850
Fondo Verde (Municipal funding)

Palencia 21 cisterns $7k Tallahassee RC(+ balance of excess from other projects)

Vivienda Urbana (Cap II) 25 cisterns $3800 dsg Tallahassee, $6k Tallahassee, $7k Walla Walla

Grand Total of 213 cisterns:

No comments:

Post a Comment