Presita de Santa Rosa Inauguration of Sapasma II project

The community of Presita de Santa Rosa celebrated the completion of 21 cisterns in the first phase of the water cistern project in their community.

The 20 family cisterns were funded by the Sapasma II project & the pilot was generously funded by a private donation from Chris.

I was unable to attend, but Enrique from San Miguel Midday Rotary had this to say
"On Presita de santa Rosa saturday visit, it was also a great event.
We met at the school patio, representatives from SAPASMA, CEDESA, Rotary MD, local beneficiaries and +- 8 communities... also I. Soto (a Green Fund member) and Miguel Gil (Rotarian and Social Development Sub-Director) participated.
Agenda was well structured, including community experiences ("you make a dream come through", remarked an old woman) and short speeches from representatives. Holly read a synthesis of the whole project evolution with hard data per communities and beneficiaries.
I brought an ecoStove for promotional purposes and which we raffled to the attendees at the end of the meeting... Ing. Fco. Jimenez SAPASMA Director agreed to help with $250 pesos
Then we had a good meal, with background music and a lot of fun people."

Monday, November 21, 2011

Presita de Santa Rosa Pilot 21st-25th Nov


The Pilot at the Presita de Santa Rosa Primary School went ahead on the 21st to the 25th November.

This pilot was funded by a private Donor - Chris Hosford, as part of the Sapasma Project II, where by the time the funding was received the prices had risen & we were no longer able to completed what we had committed to 3 mths earlier... Thankfully we have people like Chris to come to our rescue...

20 individual cisterns are being constructed by the families participating in this first phase at Presita de Santa Rosa, as part of the Sapasma Project II (funding in total 59 cisterns).

Unusually there were a majority of men working at the Pilot, when I jokingly referred to the fact that it was usually the women working & the men only on weekends, sadly they said they were on "compulsory" vacation ie they were all out of work.

They are currently all working on their individual family cisterns now & due to be finished approx middle of January...

Friday, October 28, 2011

Happy Update...Sapasma Project II

Work with the Consejo (citizen's council) continues, they meet around 6wkly & continue to provide priority for water projects, dry toilet projects & other issues. As a result of their continued hard work, we have now been successful in achieving funding for 2 more major projects. One with Sapasma (detailed in this post) & the 2nd with another Rotary Global Grant (see separate post)

Sapasma (our local water authority) have agreed to fund another project for 59 cisterns mxn$439,399 pesos. This project will be carried out in 3 communities with an additional 3 solo cisterns to be provided in 2 more communities.
Los Torres will carry out phase III & construct 18 cisterns.
Presita de Santa Rosa will carry out phase I & construct 20 cisterns - with an additional cistern being funded by a private donation - thank you Chris - & thank you Holly for arranging this.
Cienega will carry out phase II & construct 18 cisterns.
Cinco Senores will work with University de Leon & receive a single cistern.
Rancho Bonito will receive 2 single cisterns...

Paperwork is currently being completed & funding is expected to be received this week, with 1st Pilot in LT scheduled to kick off on 7th Nov.

It will be a punishingly tough rollout, with every effort to get things underway before Christmas!!

Wednesday, October 12, 2011

2nd Mtg of the Presita de Santa Rosa Potential Water Project

Where: Presita de Santa Rosa, off the GTO hwy, on the right just past Cienegita Bridge (approx. 40 mins from SMA)
When: Wed Oct 12th 2011
Who: Saul, Holly, Chela (Cedesa), Laura (Rotary), delegado Jose Luz Ramirez Vazquez, 20 adults incl 6 men, + 4 kids
Purpose: 1st Planning meeting for Sapasma funded water project. (from Sapasma Grant II)

Saul opened the meeting, describing why we’re here, & the history of our collaboration with Presita, including previous meetings & visitors to other assemblies from Presita. Presita also sent a mini commission to visit Cedesa approx. 1 yr ago.

Roberto, one of the members of the PSR community is also the secretary of the Consejo formed as a result of the water projects in the region.

The Roll was called, there were 20 on the list & 3 absent from that list.

Saul called for a co-ordinator & records taker & explained the reason & process (as we do at each meeting), Mayra was proposed & Mayra proposed Erica. A vote was taken & Mayra was appointed. Roberto was appointed records taker.

Mayra called for points for today’s agenda:
1. Cisternas
2. Contamination of Pozos
3. The process of construction of cisterns
4. Dry toilets
5. Roberto would like a mini commission to attend the Consejo, not just him
6. Organisation of groups
7. Taller at Cedesa changed to November

Chela re-iterated the involvement of their community in the process to date & reinforced that this is the reason they are now about to receive resources to construct cisterns.

She asked who knew the process of the construction of the cisterns, one young guy said he understood it was done in working groups, families banded together to build all cisterns for all families in the group. Another said they had heard they were going to be at the same time as Cruz del Palmar, & were now starting earlier?

Item 1 – contamination of water
There was general discussion about contamination, causes, symptoms etc. PSR have had water from the Banda Sapasma well for 5 yrs. Before that they had only small family wells & water from an irrigation well. They observed they have what seems like high concentration of sodium in the water as there is a lot of white build up on taps…

Saul explained that we had done a study & taken water samples of many wells including Banda, as a way to establish a baseline re our continuing study with Tierra Blanca to determine the cause of the high cancer rates they have there. The testing had been done by Unam & the Consejo on the Banda well & it was discovered to have very high level of fluoride, 3.47 (highest max safe level is 1.5mg/l).

This is a serious problem in this community but also in this region in general, causing damage to your health & that of your children, which is one of the main reasons we began this project in 2008.

There are more than 300 families currently using this well in Banda, & many are unaware of the situation with the contamination, you need to tell the communities (your neighbours) this information – one of the women joked “we don’t drink much coke, sometimes wks go by, but now we cant drink the water either – what can we drink?”. We all laughed & said, exactly, that’s why we are catching the rain water to drink.

At this point Chela took the floor to discuss junk food & it’s damage to health, & the benefits of eating healthily v the strain we put on our bodies having to process the chemicals & food colouring in junk food. Saul pointed out that initially there will be resistance by their families to eating healthy food, but once everyone is used to eating healthy food it becomes very difficult to tolerate junk food anymore… & just need to break the habit.

Item 2 Cisterns/project planning.
Apparently there are approx. 44 families in Presita & so only approx. ½ have stepped forward to participate (we have found this to be common in the communities, there is always an initial group of motivated early adopters & later the others “get” the idea & we have to do a phase II)…

It was decided the pilot training session will be carried out at the primary school.
There are approx. 30 children at the school.

The list of participants was transcribed for all to see.
There were 18 firm participants at that point. There was one other woman, not here today (since her kids are sick) who has been participating & it was voted to add her – Isabel.

Another woman was visiting for the first time & asked to be included, there was a lot of discussion about people’s ongoing work for over a year, & she had been invited but not participated previously & was just showing up today to get on the list.
“if you’re not part of the meetings you shouldn’t expect to get rewarded with a cistern”. “We’re not just working on cisterns, she should be involved in the other meetings too like the regional meeting in La Tinaja – there’s lots of work going on”
Eventually it was agreed she could join the group, there was a talk about possibility of her having to pay a fine, but nothing was agreed.

Groups were formed as follows: A= Abanile, C= Co-ordinator
Group 1 7 families Group 2 7 families Group 3 6 families

20 Families + 1 pilot = 21

It was confirmed that water would have to be carried to the school for the pilot.
(approx. 3000 litres per day)

Community Co-ordinator was appointed – Hortencia + backup Roberto

PVC & Gravel will be delivered to one central location & collected from there to the house of Rosalia

No date has been set for the pilot, until we know when the $$ will be received, which is reliant on deciding the 3rd community (Currently Los Torres 19, PSR 21, 3 solo cisterns + 19 ??? – this is being decided at the Consejo meeting tomorrow)

Chela reminded everyone they need to work hard to make this project as success as future project funding is riding on this.

She explained that the process of building the cisterns is carried out to ensure that all cisterns advance at the same rate, ie all wire weaving done first, then the next step, applying cement etc, so they all finish at the same time.

They need to meet as groups to decide their hours of work & rules, ie fines if no work, Saul suggested the person breaking the rule might have to provide carnitas for everyone!

Tools – Saul listed the tools needed on the first day of the pilot, including grinder to make the small hooks needed to weave the wire & mesh together… scissors for cutting the wire, cutters for the maya etc, & also suggested they bring something to rest their knees on while they are kneeling to do the weaving of the wires.

Item 3 – Sanitarios Secos (dry toilets)
This community along with most of the consejo communities, was part of the solicitud to govt to construct 400+ cisterns in 18 communities. Chela gave an update of the situation with the resources Lucy had given them, that the $4million + pesos comes with a requisite to have outside contractors (& a bid process), which excludes them from being able to build them themselves, which was what they were hoping for to be able to stretch the $$ to provide more toilets for more families.
The Promoters from Desarollo Social have been visiting the communities to create a list of recipients (once they check they have no form of toilet – functioning or not – to be able to be eligible)… They have not visited Presita yet.

Item 4 Representation at Regional Meetings
Roberto is feeling like it is a lot of work to be secretary of the Consejo as well as to have to advise his community of “goings on”. He has also not received any contribution to his costs from his community, whereas other communities have supported their representatives. There are at least 4 people who are on the list of reps. of the Consejo, but have not been attending as they have not been informed, lack of communication is a common issue in the communities, as no-one has phones & they live a long way from eachother. It was agreed that advice of meetings will be given to Roberto & he will in turn inform the other reps. to ensure all know when the meetings are on, & they will begin to share costs of transport.

Item 5 Taller – Workshop at Cedesa
Saul explained that training & ongoing improvement is a way to increase people’s standard of living. Cedesa & the Consejo are committed to the process of integral development & ongoing work (not just completing the projects & that’s it!)… Part of this process is to continue to share information & learn new & better ways of doing things. As part of this process Cedesa holds regular workshops for campesinos on various techniques & information. There is an upcoming Workshop planned for 19th November 9am-5pm at Cedesa

The topic of this workshop is Food, & Alternative Medicines, Saul asked if anyone could define what Alternative medicines meant, one young man responded “ there are plants with curative properties, it’s about learning these”.

Saul explained - included in the Food topic will be how to construct a nopal tunnel – why Nopal? Because it’s one of the most noble plants in our region, it provides so much & is such a healthy option so if we take care of these we can ensure better production.
A commission of 3 can come from Presita (& all other communities) & report back & organise groups to learn at people’s houses, ie to interchange the information.

Chela reiterated the objective is to learn to produce food, since grains & beans will be a big issue this year, with failing crops & lack of rain. Change in climate has been a big issue & we need to adapt & ensure we work hard on alternative food production.

At this point the meeting was declared closed, one of the older women had left the meeting early to prepare food for us (visitors), she came back in struggling to carry hot pots of lentils & pasta soup with calabasa… & THE most delicious tortillas I’ve eaten!

There was no date set for the next meeting/pilot (this will be done by phone once we know the date of the receipt of funds).

Wednesday, August 25, 2010

1st Mtg of the Presita de Santa Rosa Potential Water Project

Record of Event pg 1 of 3
1st Mtg of the Presita de Santa Rosa Potential Water Project

Where: Presita de Santa Rosa, off the GTO hwy, on the right just past Cienegita Bridge (approx. 40 mins from SMA)
When: Wed Aug 25.8.10 11.10am
Who: Saul, Holly (Cedesa), Laura (Rotary), delegado Jose Luz Ramirez Vazquez, 25 adults incl 7 men, 7 kids, 3 dogs

Purpose: Initial meeting to determine community needs, outline Cedesa & explain the water projects process.

Representatives from the community of Presita had come to previous assemblies at neighbouring Capaderillo, asking about the process re the projects. They invited us to visit to know their community more. This is our first visit.

We were met at the turn off from the highway & guided to the community Salon.
It was constructed as part of a govt. program through CONAFE. This is the only community we have visited that have a public meeting place.

As we arrived women were bringing buckets of food, tortillas wrapped in embroidered cloths, rice, beans, casseroles, we thought they were for the kids who they feed at 11am at school each day, but we soon found out it was for us!

We entered the Salon, it was decorated with brightly coloured pictures for children, & I noticed what looked like a “toy library” in one corner.

We were presented with a list of the 157 people in 58 families of the community.
We noted the families were very small, mostly 3 or 4 people, unlike other communities which have been on average 7.

We asked if there were a lot of men in the USA, they said no maybe 3 or 4, the majority are still in Presita…

We were waiting for the rest of the community to gather & they insisted we eat first & then have the meeting. The food was delicious & including lentil casserole, chickpea casserole, wild greens, especially nutritious.

We revised our visits, their first was to Vivienda de Arriba on the 7th July, & 2nd was to Capaderillo on the 11th Aug, attending assemblies & asking for us to visit their community.

There was a young boy sitting on his grandmothers’ (Maria Isabel’s) knee. His name is Jesus, he is 3 yrs old & obviously handicapped, very cross eyed, rigid body movements, I asked about him & apparently he can say 3 words – Mama, Papa & Agua! He demonstrated cognitive behaviour, was sucking his thumb & can drink from a cup held for him.

An older woman came in late with a particularly huge container of rice & placed it at Holly’s feet saying it was for the “chinita” – Holly is Japanese American & looks Asian to her I guess. There was a lot of laughing, as Holly’s reputation as a big rice eater had obviously preceded her!

After eating, we got down to business..



Record of Event pg 2 of 3

Introductions
Saul asked everyone in the room to say their name, this is usually a good way to break the ice as many people are embarrassed to do this, & it usually results in giggles!

Saul, Holly & I introduced ourselves.
Saul asked why we were all here.
1. To find out more info & how to get cisterns
2. One woman has a woman in Vivienda de Arriba (another project community) & wanted to know how to get cisterns
3. I don’t have clean drinking water, no running water, I have to call & ask for Pipa (water truck) to come & pay for it.
4. In the upper section of the community we only have water in the rainy season, no water in the dry season (the majority of the year)
5. My children & myself have teeth turning yellow, I think it is from the water, I would rather drink water from the sky.

Jose Luz (the delegado) went to the presidencia & was told by Ecologia dept, that there is an NGO helping resolve water issues. He was ver surprised we would respond so quickly.

Holly described Cedesa in a general description, being all about the development of communities & achieving communities to achieve sustainability & self reliance.

I described Rotary & what it is all about & the global service aspect.

Saul & Holly explained we are not here to help you but to work with you to achieve resolution to issues. We come & meet with the communities, get info regarding their water & their situations & work towards finding resources to resolve the issue.

Currently we are working on 3 sources for funding, Rotary, Sapasma (local water authority) & Fondo Verde (green fund – part of the Ecology department of the local council.

None of these sources are certain, they are possibilities re assisting with resources

1st step is to collect statistics by community & then collate by community, then we can attempt to find the necessary resources together.

Saul gave a brief history of the projects, that Los Torres, Montecillo de Nieto, Vivienda de Arriba & Cruz del Palmar were all funded by Rotary, & that Capaderillo is the first govt. funded project.

The commitment from the communities includes working together & participating in assemblies.

Holly reiterated that it’s not just about working to build the cisterns, but also in participating in the organisation process & learning collaboration.

Saul – today’s objective is to meet & know the community better to see what we can do together. He mentioned a change in the way Rotary funds projects & that it now makes sense to combine multiple communities in the region to work together in one big project.

Saul suggested forming a commission who can continue to co-ordinate the community & attend assemblies in Capaderillo & report back to Presita.


Record of Event pg 3 of 3

One of the women described what she knew of the project process in Vivienda de Arriba, that they all worked together, agreeing what hours they would work & then committing to it.

Laura (with Holly’s help translating) described a little of the process of the project, what was involved, from pilot, to attending assemblies etc & the level of commitment expected.

These points were raised
• The 12,000 ltr cistern is sufficient for a family of 14 for drinking & cooking for the whole year.
• It’s a good idea to share cisterns if there are 2 families living near
• Older people can not help with the heavy work, but can participate & it may make sense for them to receive plastic tanks if they are living solo
• Lots of young families in this community it is a new community
• 40 years ago there were only 4 houses here.
Saul provided the delegado with a copy of the general community questionnaire.

Holly suggested a commission should come to Cedesa to know more about them

The commission to represent Presita at assemblies will be
Mayra Guadalupe Ramirez Ramirez (“she is very interested in learning more” )
Maria Apdonia 415 119 2361
Joze Luz 415 155 9453 (Delegado)
Lionel Gonzalez 415 119 0737 (this is the young man that went to the presidencia)
Rosalia 415 149 3920
Rita Gabriela/Antonio

Action – (Lionel) will come up with a list of people who wish to visit Cedesa in approx. 2 wks. Holly will co-ordinate this visit with Lionel.

Next assembly will be representatives attending assembly at Capaderillo 8/9/10 at 3pm