Thursday, December 15, 2011

1st Meeting at La Lomas de Cocina/El Ocote Sapasma II Water Cistern Proj + Stove Proj.

Record of Event

Where: La Loma de Cocina

When: 15 Dec 2011

Who: Saul, Laura (& Fili – tech asst) + 18 community members from Lomas including Abel (from Cedesa – he lives in this community) & later 11 women from El Ocote (neighbouring community).

Purpose of the meeting: To visit the 4th day of the solo cisterns Project for Sapasma II Project & witness & participate in Stove Demo.

Background:

Sapasma requested that materials for 2 cisterns be made available from their Project II grant the community of Rancho Bonito. It was intended that Sapasma organise this community & we do a pilot there to get the 2 cisterns built for this community in need.

Unfortunately the people of Rancho Bonito were not able to organise to build these 2 cisterns which was only discovered after the delivery of the materials. A large component of the materials is the cement & cement has a limited shelf life of approx 2 wks so it was imperative another location be found for these 2 cisterns…. Luckily the community of La Lomas de Cocina had been organising with Abel (new Cedesa Promoter) for approx 8 mths & were very willing to take the materials & get the cisterns built so the materials were hastily re-delivered to Lomas & the construction took place 2 days later.

The day unfolds:

I followed Saul out to this community as I had not been there before.

We left SMA at 8.30 & arrived at 9.30, as the crow flies it is not that far, but it takes a long time to arrive there!

When we arrived the cistern group was busy working on the cistern.

A little later a group of women arrived walking from neighbouring El Ocote.

They pointed out in the far distance a wáter tower & described themselves as “close”, distances have a different meaning in the campo.

We had a very informal meeting, more of a Q& A session & Saul prefaced it by, they probably havent met too many foreigners before but not to be nervous, that I was the same as them, they said they’d never met a foreigner who could speak spanish before. I laughed & said they still hadnt…

They told me (or I think they told me – unfortunately we didnt have Holly there to help with translations!)

  • La Lomas has approx 90 families
  • El Ocote approx 32
  • Test had been done on the wáter it was fluoride 1.7 mg/l, & arsenic 0.030, if there was wáter,
  • they had not had wáter for 2 months. The Wells deplete as there is a major agribusiness right next door.
  • The agribusiness is the major employer, but many have been layed off lately.
  • None of the men are working in the USA right now, they have a history of being agri workers for the big agribusiness, they are not abaniles, hence can not find alternative work.
  • They have a kínder in each community – La Joya (other neighbours) 12 kids, Cocina 21 kids.
  • Primary school in each community – La joya approx 20 kids, Cocina approx 80 kids (kids from El Ocote attend Cocina school)
  • They have only 1 computer in the school
  • Some have dry toilets
I asked what they considered their major need, economy was high on the list as were water issues. We talked about possibilities, raising chickens, selling eggs at the organic market, raising turkeys, possibly rabbits?

Saul joined our meeting & asked them what the issue is with Arsenic & Fluoride. They were not certain, some knew a little, Saul explained that it affects the brains, bones & all major organs, if it is affecting your teeth it’s definitely affecting other parts of the body too.

He explained that the materials for these cisterns are courtesy of Sapasma, & were moved to their community as the people of Rancho Bonito did not want to work to build the cisterns, & that the wáter these cisterns will capture is important to the health of their family & community, but as important is the need for them to continue to take responsibility for improvements in their lives.

“Who brings your food?” They respond that they produce a little in summer but mostly buy their food. Saul explained it was better if they take control of their own food production, for many reasons including the quality of the food they will therefore be eating.

There was a little discussion about backyard production, I thought they had been working with Ezekiel from Apoyo on this they said, no they have been working with Abel from Cedesa.

Saul asked how they build cisterns & took the op. to describe integral community development, health, economy, agriculture, how they are all related. He reiterated that solidarity & working together to assist eachother is essential, as is respect for eachother & together they can achieve an increase in standard of living for all, ie improve their own conditions.

Even though they have a Sapasma well, this year they have already been without wáter for 2 months as the wáter table has dropped so low. They also said they have a shortage of Wood too & Saul explained they need to plant trees that will provide Wood & maintain their trees, & that the stove he will demonstrate later also uses a lot less Wood.

They meet monthly with Abel & are working on various things for example, working together to buy a molino (grinder for maize), they have also been learning how to make bread & galletas for sale in the big ovens that Cedesa demonstrates, as well as planning to grow excess veges for sale.

Saul suggested they could have (or they have been having, not sure) a “tanda”, each person contributes $100 pesos per month, & can build one pizza oven per month.

Saul explained about the Consejo (regional citizens’ council) 21 communities who meet 1x per month & work on common issues, he suggested each family could contribute 5 pesos per wk & have sufficient funds to send a couple of representatives to this meeting each month.

He said they would be surprised how rapidly the money accumulates if they choose to save it instead of purchasing coke everyday.

The women came & dragged me into their “kitchen” they cook on a fogón (open fire) inside a room with a space between the Wall & roof on one side. The walls were pretty black. They were making gorditas & insisted on showing me how & I gave it a go. It is certainly harder than it looks, but they have all been making them since they were little kids & found it pretty funny that I, at my age, had no idea!!


Lesson on making Gorditas...

The process to cook/soften the maize until it can be ground to flour (fine for tortillas, more course for gorditas) is to cook the maize over a fire with wáter & lime (as in cal, not the fruit), for an hour or more (depending on qty) until it softens slightly (to biteable) & then cool it, remove the wáter & grind it.

We stood around the fire, with a large comal & first slapped the mixture into shape rotating our palms in opposite direction, while keeping the edges uniform (& unsplit – them, or Split me!!) then we gently lowered onto the comal & kept an eye on all of the gorditas sitting there, when they looked cooked, or dry enough, gently peel them at the edges & flick them up & then lowered them back onto the comal to cook the other side… After they were cooked, they were Split with a knife & filled with various previously prepared mixtures of shredded chicken, egg, beans, red rice & guacamole.

At the same time the demonstration of the ecocina stove was started, Saul explained all the benefits & the process of lighting it, & cooked some quesadillas for everyone. This was about when I was dragged in to cook gorditas so I didnt see the end result, but I believe he reported this in his report.


So many tortillas/quesadillas can fit on this comal!


These photos show the overlap of two projects, the cistern project & the stove project

I then headed off, Saul asked one of the women from El Ocote to accompany to show me a “short cut” which was a real offroad experience, we followed a very rudimentary track between many cactus, & eventually came out on a sealed road, my guide left me at this point & pointed me in the right direction.

I picked up a woman walking beside the road & she turned out to be the Govt registrar for the área. She Works in a little office in this community & services approx 10 surrounding communities, registering births, deaths & marriages. The office she reported to was in Dolores Hidalgo, I asked if she knew of Cedesa, she said yes, of course, she knew Chela, small world. I ear bashed her about the projects, & then we stopped & picked up a Young woman & Young boy, they were heading to the highway & were surprised by how warm it was in the sun & happy for the lift… The woman registrar explained what I had just told her & so she too was “informed”…

We parted ways at the Dolores Highway & I headed home.

See photos on the blog http://ecocinastovemexico.blogspot.com/ also.

Wednesday, December 14, 2011

Stats update 14 Dec 2011

Below is a list of all the Projects completed, in progress & pending...

All up we expect to have completed total of 407 by Mid January 2012, with an additional approx 108 to be completed approx mid March. (grand total will be around 515 cisterns - & counting!!)

Average family size is in our communities is 7 members, x 515 = 3605 (this figure is conservative as many of the cisterns have been placed in schools with average number of beneficiaries being 80).

Projects in Process:
Sapasma Project II mxn$435399
18 cisterns in Los Torres (Phase III in this community) Pilot completed 14-18th Nov, individual cisterns to be completed by mid January 2012
21 Cisterns in Presita de Santa Rosa (Pilot paid for by private donation - thankyou Chris Hosford, 20 cisterns funded by Sapasma)
18 Cisterns in Cienega Juana Ruiz (Phase II in this community)
2 Cisterns in Lomas de Cocina
1 Cistern in Cinco Senores
(all of these cisterns are expected to be completed by mid January.

Project Pending:
$65.3k global grant application stage with Chinook RC in Calgary Alberta Canada, with contribution of $20k by Alberta Government from their Community Initiative Project - Thankyou CIP!
This is to be approx 108 cisterns constructed in 3 communities -
Tallahassee RC has pledged a further $10k to help bridge the price increase in materials since the budget was presented

The projects below have all been completed...
347 to date with more plus the additional ones in construction & in planning.

Tierra Blanca 28
Juan Gonzalez 22
funded by Global Grant from Baton Rouge Capitol City RC & District 6200 US$33,500
(completed June 2011)

Tierra Blanca 14 - direct grant donation from New Braumfels RC $2k, & Port Lavaca RC $7k
(completed June 2011)

San Lorenzo 4
Cinco Senores 11 (incl pilot in JG)
Fondo Verde Mxn$150k
(Completed June 2011)

Villa de Guadalupe 27
Cienega Juana Ruiz 26
Sapasma mxn$435k
(completed June 2011)

Villa Pilot x1
Cienega Pilot x 1
Bellingham RC US$1500
(completed June 2011)

Tierra Blanca completed all 42 cisterns in record time of 5 weeks!!

Water Projects completed from 1st Jan 2009 - March 2011

Los torres 52 cisterns - done in several phases.

Phase II Project : $21,200
Direct Grant Rotary Club Partners amount committed:
RC SMA Midday Mexico 200
Tallahassee RC USA (Bill Webb) 4000
RC of Sechelt BC Canada (Tom Pinfold) 5000
Paso Robles RC USA (Robert Lata) 500
Tyron RC (Jerry Atkins) 5000
RC of Ann Arbor (Len Stringer) 6000
US$ Total of Rotary funds committed 20700
Plus! $500 donation from Skymed/Linda Scholey $500
(this funded 27 in this phase + excess $$ funded 4 extra cisterns & 3 rotoplas added to the phaseIII)

Phase III project: $12,200
SMA Midday 200
Tallahassee 1000 DDF 2000
Tyron RC 2500 DDF 2500
Ann Arbour 1500
Sechelt 1500
Trail BC 1000 N/A
Subtotals, Cash and DDF 7700 4500
San Miguel Community Fund (SMCF) funding grant 1 $2468 SMCF funding grant 2 2235,
(this funded 17 cisterns)


Montecillo de Nieto 30 cisterns $16700
SMA Midday 200
Tallahassee 5000 DDF 11500
Unitarian Universalists funded 4 months of organisation in this community. $400 per month.
Vivienda de Arriba 17 cisterns & Cruz del Palmar 28 cisterns for a combined $24700
SMA Midday $200
RC West U $4500
RC Richmond $3500 District 5890 8,000
RC Tallahassee 2000 DDF 6940 6,500
Subtotals, Cash and DDF 10200 14,500


Capaderillo 40 cisterns $21850
Fondo Verde (Municipal funding)

Palencia 21 cisterns $7k Tallahassee RC(+ balance of excess from other projects)

Vivienda Urbana (Cap II) 25 cisterns $3800 dsg Tallahassee, $6k Tallahassee, $7k Walla Walla

Grand Total of 213 cisterns:

Tuesday, December 13, 2011

report re completion of dry toilet in Vivienda de Arriba



The completion of the dry toilet was undertaken in Vivienda de Arriba with some remaining funds from a direct grant from Tallahassee & Walla Walla Rotary Clubs.

This dry toilet was begun by a colleague working with Cedesa but was not able to be completed as they ran out of funds...To the rescue came Tallahassee & Walla Walla, & thanks to them, Cedesa & the community, they now have a dry toilet for public use beside the chapel in Vivienda de Arriba. An excellent demonstration example for not only their community but also visiting communities.

Following is the report submitted by one of the young men working on the project.
Un Cordial saludo a Laura Stewart & Club Rotario Walla Wall y Club Rotario Tallahassee.

Estamos felices por haber concluido el proyecto de sanitario seco el cual gracias a club rotario con ayuda de CEDESA pudimos dar por terminados.

El trabajo fue concluido con ayuda en mano de obra por parte de la comunidad por el cual se termino en cuatro días lo que nos permitió tener una convivencia con las personas de la comunidad. Para el trabajo formamos grupos de 7 personas para cada uno las personas de los otros grupos también participaban los días que no trabajaban llevando comida para los compañeros que andaban trabajando. Gracias a este proyecto hubo una buena comunicación entre la comunidad.

Habiendo concluido con este proyecto, entregamos notas de todo el material comprado al igual que fotos donde se presenta la comunidad en el trabajo.

Hacemos la entrega de la cantidad de: $294.00 pesos dinero sobrante de los fondos del proyecto.

A nombre de la comunidad de: La Vivienda de Arriba damos las gracias por haber recibido el apoyo para terminar el sanitario seco para la Iglesia.

DE ANTEMANO GRACIAS Y HASTA LUEGO.

Wednesday, December 7, 2011

3rd Meeting at La Tinaja re Water Cisterns

Record of Event

Where: La Tinaja Community – Health Clinic

When: 7 Dec 2011

Who: Holly, Saul, Chela & Laura + 18 community members including 1 man + 7 kids

Purpose of the meeting: To plan wáter cisterns Project re the Calgary Global Grant.

People were absent today as another community meeting was being held at the primary school at the same time.

Chela opened the meeting & asked who would be co-ordinator & record taker for the day, since it was a small room & we were all sitting there freezing & couldnt easily see a board since we were in a circle, we ran the meeting informally, just recording actions in their minutes book.

She also asked why the community representatives from La Tinaja did not attend the regional meeting 26/11 at Juan Gonzalez or the training workshop 19/11 at Cedesa. They sheepishly admitted they forgot.

Chela reminded them that if they dont continue to meet or attend meetings they are failing their commitment, it doesnt matter if you happen to have an appointment that clashes with a meeting you have a responsibility to attend or send someone in your place. She asked what people think will happen if they stop attending meetings & working together, they were embarrassed to reply.

She reiterated that at Cedesa workshop it was only La Tinaja & Cinco Senores who were absent, there were representatives from all the other communities & a turnout of more than 70 participants when it was planned only approx 50 would attend At Juan Gonzalez regional meeting it was only La Tinaja absent, more than 100 people turned up for that meeting. You will forfeit your right & priority as attendance in meetings is a major part of the commitment.

We all agreed La Tinaja is very remote & it is difficult to travel to the other places as they are so far away, as well they have no telephone or cell phone service, so they need to stay in the loop of what is going on with their friends at Villa de Guadalupe (the nearest community).

They were asked to take initiative & fin out the dates of events etc, Alicia, Audelia & Dolores are the Consejo reps, they will advise the rest of the community “we need all of you to take responsibility to continue to work together to improve your living conditions, cisterns dry toilets & other things, if you dont want to that’s up to you, but you need to continue to participate to be part of ths, take account now, improvement in your life & living conditions is up to you, organise & participate together.”

We advised that funds for the cistern Project will be ready in January, Chela asked “what do we need to do next?” “decide which groups we work in” was the reply.

The roll had been called earlier & found that 3 were missing. Work groups were formed, including the appointment of a leader, & number 2 in each group, abaniles in each group & the co-ordinator for the whole Project (ie the person whom each group reports to, who in turn reports any issues to Saul – the regional co-ordinator).

One woman voiced her doubt about her husband being willing to help, & that she didnt feel she could volunteer him, Chela & Saul both explained this Project is for the benefit of all & therefore very important that everyone work together. The cistern needs not to be absolutely perfect (ie with expert masons) but just need proficiency.

There was a description of responsibilities, ie to attend each of the training days, to turn up on time, work in harmony, report issues to your group leader. The leader will work directly with the co-ordinator & the co-ordinator will report back to Saul for any issues regarding tech assistance, materials, deliveries etc.

Adela was voted Co-ordinator for the whole community.

There was discussion re the location for the training Pilot.

Debate was:

Primary School – 200kids, there for 6yrs, have wáter sometimes, other times are forced to drink from the river.

Kinder – 9 kids, there for 3 yrs, don’t have any wáter.

Decision was Primary School.

Meeting closed, & next planning assembly is 18 Jan 11am